Desk note · Public money · Broadband

Idaho’s $120 Million Broadband Builds Have Two Months Left

Eighteen federally funded broadband projects are due December 31. The state’s own report says “79% of projects on track” but doesn’t say which ones aren’t.

Based on public documents. No interviews were conducted. We are sending questions to the Idaho Office of Broadband and will update this note with any response.

Eighteen broadband projects paid for with Idaho’s share of the federal Capital Projects Fund are due to be finished by December 31, 2026. The Idaho Broadband Advisory Board awarded the $120 million in December 2023 to 15 recipients, who added more than $58.8 million of their own, according to the state.

The clearest public look at progress is the state’s annual performance report to the U.S. Treasury, covering July 2025 through June 2026. The Idaho Office of Broadband posted it in July in a file marked Draft V3. Its progress graphic says “79% of projects on track.” Fourteen of 18 would be 77.8%; fifteen would be 83.3%. The report doesn’t say how the figure was calculated or which projects make up the rest.

Bar chart of Idaho’s $120 million in Capital Projects Fund broadband awards: $6.3 million in two completed projects, $48.6 million in eight projects with delays or risks named in the state’s report, and $65.1 million in eight others.
Original explanatory illustration by The Idaho Stack. Award amounts from the state’s awards list; status from the state’s performance report. “No delay named” means the report excerpts we reviewed don’t flag the project, not that it is on schedule.

The projects the report flags

The report does name problems. These are the projects it singles out:

Flagged in the state’s performance report, July 2025 to June 2026
ProjectCPF awardWhat the report says
Gooding County$7,509,334The city denied a special use permit for the Wendell tower, with reconsideration pending. The county “has requested a six-month extension to its period of performance.”
Camas County$5,090,021About 16 months to win a conditional use permit for the Steve Miller tower, which an adjacent landowner has now appealed. A permit-exempt tower design lets work go on meanwhile. The Fairfield tower is done and serving 226 customers.
Intermax Networks: Highway 54, Hauser Lake, Selle Valley$13,789,516 (three awards)Some locations lack private road permission and “may ultimately remain outside the final build” without owner approval. Selle Valley needed about 18 months of wetland study before construction.
MiFiber: Priest River and Oldtown$6,259,110Long make-ready waits with utilities, Inland Power in particular, forced schedule updates. The report says it remains on track.
Idaho County: Orofino to Grangeville$11,589,881Lengthy pole licensing talks, rail crossing permits, and severe weather including federally declared disasters.
White Cloud: Owyhee County$4,357,749Delays at the Oreana tower site, including lease execution and local planning approvals.

Some work is finished. Lincoln County’s build is complete, with more than 294 locations passed and 185 active connections. The report calls Ziply Fiber’s Aberdeen project complete, with service available to 734 locations. Comcast’s Preston-area build reached about 96% construction completion during the year.

The report says little about Latah County’s $15 million dark fiber project, the largest single award.

What changed after the report closed

In May, Treasury updated its Capital Projects Fund FAQs to let states ask for a six-month extension, to June 30, 2027, for broadband builds. Requests were due July 31, 2026, and only the state, not providers, can file. Treasury says it will approve one only if a project has made material progress, spent money on it before May 31, 2026, and been delayed by circumstances beyond the recipient’s control.

The report period ended June 30, so it doesn’t say whether Idaho asked, or for which projects beyond Gooding County.

One caution on the headline numbers. The report counts more than 30,000 locations “passed or able to subscribe to service” and more than 4,000 active subscribers, but much of the network was still being built, so the two don’t make a take rate. Where builds are finished, it gives one: about 63% in Lincoln County and 35% in MiFiber’s completed areas.

What we’re asking

We are asking the Idaho Office of Broadband which projects are not on track, whether Idaho requested Treasury extensions and for which projects, and how much of the $120 million has been paid out so far. The report gives no spending figure for the broadband projects. We’ll add the answers here.

Sources and limits

Public records reviewed November 1, 2026.

Figures are as the state reports them; we have not audited them. Award amounts are grants, not money spent. The report is a draft and may change.