1Kuna · Ada County
Meta Kuna Data Center
OperatingLast change Sep 4, 2026
- Developer
- Meta Platforms (utility customer of record: Brisbie, LLC)
- Size
- 960,000+ sq ft
- Investment
- $1.2B Meta’s 2026 figure; $800M when announced in 2022
- Status
- Serving traffic as of September 2026, according to a Meta executive’s post reported by Baxtel. Announced February 2022 with about 100 permanent jobs.
- Tax break
- BoiseDev describes Meta as eligible for the 63-3622VV sales tax exemption. 2025 Senate committee minutes record conflicting testimony on whether the Tax Commission granted it. No public record shows the amount. Our note.
- Power
- Special contract with Idaho Power under the name Brisbie, LLC, approved by the PUC May 11, 2023 (case IPC-E-21-42). Meta says it added 645 MW of new renewable supply in Ada County to match its use. Neither Meta nor Idaho Power has published the site’s load in megawatts.
- Water
- Meta transferred about 2.5 million gallons a day of farm water rights to the City of Kuna and runs the site on a separate system. Expected summer peak use is just under 2 million gallons a day, BoiseDev reported.
- Local rules
- Inside the Kuna East urban renewal district, created in 2022.
Sources (5)
2Kuna · Ada County
Gemstone Technology Park
On holdLast change Jun 15, 2026
- Developer
- Diode Ventures, a Black & Veatch subsidiary (applicant: Gemstone Technology Park LLC)
- Size
- 620 acres, up to 5 buildings
- Investment
- $1B “more than $1 billion,” per the developer
- Status
- Kuna approved the rezone April 1, 2025, on a tie broken by the mayor. Neighbors sued; a district judge denied their petition in May 2026 and they appealed to the Idaho Supreme Court in June. No hearing date was set as of August. Design review is still ahead.
- Tax break
- Could qualify for 63-3622VV, BoiseDev reported. No record shows a claim.
- Power
- Idaho Power has completed a feasibility study; the developer says it will pay all interconnection upgrades. No PUC contract found. The Idaho Conservation League estimates 600 to 800 MW; the developer has not published a figure.
- Water
- Plans to move three irrigation water rights, about 1.63 million gallons a day, to industrial use through a pending Idaho Department of Water Resources transfer, with on-site treatment and reinjection.
- Local rules
- The developer offered about $40 million to Kuna’s fire district, police and schools.
Sources (4)
3Boise · Ada County
ValorC3 Emerald
ApprovedLast change Mar 26, 2026
- Developer
- ValorC3 (formerly Fiberpipe), owned by Tonaquint
- Size
- 10 MW · 38,000 sq ft first phase
- Investment
- $20M “more than $20 million” for phase one
- Status
- Boise approved the first phase in 2025, due to open in 2027. A preliminary application in March 2026 would add 31,000 sq ft.
- Tax break
- Below the $250 million threshold for 63-3622VV.
- Power
- Not reported.
- Water
- Not reported.
- Local rules
- A colocation site inside Boise city limits, approved before the mayor’s November 2026 moratorium proposal.
Sources (1)
4Nampa · Canyon County
T5 Data Centers Nampa
ApprovedLast change Sep 2, 2025
- Developer
- T5 Data Centers, for one unnamed tenant
- Size
- 8.25 MW · 80,000+ sq ft existing building
- Investment
- Not disclosed
- Status
- Nampa’s planning commission approved a conditional use permit in August 2025 to convert an existing building in Park 84. Whether it is operating is not reported.
- Tax break
- Not reported.
- Power
- About 2.25 MW at first, rising to 8.25 MW, BoiseDev reported. Another outlet put the first stage at 2.5 MW.
- Water
- Air-cooled; the developer compared water use to one or two homes.
- Local rules
- Conditional use permit from Nampa.
Sources (1)
ProposedLast change Oct 9, 2026
- Developer
- Rhea Data, a subsidiary of Nevada-based Arevia Power
- Size
- 600 MW · About 4 million sq ft on roughly 3,200 to 3,750 acres
- Investment
- Not disclosed
- Status
- Applied to the Bureau of Land Management’s Four Rivers Field Office to use public land south of Kuna-Mora Road. The BLM expects to open formal environmental review with public comment around the end of 2026.
- Tax break
- Not reported.
- Power
- 600 MW of computing, per the applicant. An on-site gas plant of about 450 MW appears in the applicant’s early filings; the BLM has not confirmed the energy plan. Idaho Power says Rhea is not in its load forecast and any service would need PUC review.
- Water
- Not reported.
- Local rules
- Federal land, so the BLM decides, not a city or county. Boise’s mayor called selling public land for mega data centers “shortsighted.”
Unconfirmed: Acreage varies by outlet (3,226; 3,200; about 3,700; about 3,750). The gas plant size comes from one outlet’s reading of the filings.
Sources (4)
ProposedLast change Oct 27, 2026
- Developer
- Weitz & Co.
- Size
- About 3.4 million sq ft in four buildings
- Investment
- Not disclosed
- Status
- A concept was dropped off at City Hall on October 20, 2026. No land-use application has been filed. A week later the city adopted an emergency moratorium on data center applications.
- Tax break
- Not reported.
- Power
- The concept includes its own power generation and backup power. Size not stated.
- Water
- Closed-loop cooling proposed. A 2005 agreement may allow a city water connection, KIVI reported.
- Local rules
- Data centers are not a permitted or conditional use in any Mountain Home zone, the mayor said. Emergency moratorium adopted October 27, 2026.
Sources (2)
ProposedLast change Oct 27, 2026
- Developer
- Copia Digital
- Size
- About 3,000 to 3,700 acres
- Investment
- Not disclosed
- Status
- A pre-application to the BLM filed in January 2026 for public land near Idaho Power’s Midpoint substation. The developer says formal federal review is likely at least a year away.
- Tax break
- Not reported.
- Power
- Not disclosed. The site sits near the Midpoint substation, a major transmission hub.
- Water
- Not reported.
- Local rules
- Federal land; the BLM decides.
Unconfirmed: Acreage: about 3,013 acres in one analysis of the application records, about 3,700 in another report.
Sources (1)
ProposedLast change Oct 30, 2026
- Developer
- TerraVolt Holdings (formerly CalEthos), Tustin, Calif.
- Size
- 240 MW · Options on 1,077 acres
- Investment
- Not disclosed
- Status
- Announced options to buy 1,077 acres on October 30, 2026. Data centers are not a permitted use in Cassia County, so the project needs county zoning approval. Commissioners hold a public meeting November 10.
- Tax break
- Not reported.
- Power
- 240 MW of gas generation on site, separate from the grid, fed by the Williams Northwest Pipeline under a supply deal announced in May 2026.
- Water
- The company says closed-loop or low-water cooling will be required of each site buyer.
- Local rules
- Needs Cassia County zoning approval.
Sources (4)
Denied, contestedLast change Oct 26, 2026
- Developer
- Lex Developments LLC, Gilbert, Ariz.
- Size
- 100 MW · Seven buildings, about 700,000 sq ft
- Investment
- $2.6B
- Status
- Pocatello denied a conditional use permit in May 2026 and upheld the denial twice, most recently 3-2 on September 17. The developer petitioned the Sixth District Court for judicial review in late October, arguing no permit was needed in the industrial zone. It also says it plans to reapply; the council waived the usual one-year wait.
- Tax break
- Not reported. BoiseDev noted it could qualify for Idaho’s property tax cap for $1 billion-plus investments, a separate break.
- Power
- An Idaho Power feasibility letter cites more than 100 MW by 2031. The developer has also said the site could host up to 300 MW of gas generation.
- Water
- No wastewater figure was given to the city.
- Local rules
- The Shoshone-Bannock Tribes and more than 80 speakers at the first hearing opposed it. Bannock County separately adopted a moratorium for unincorporated areas.
Sources (4)
ProposedLast change Jul 30, 2026
- Developer
- U.S. Department of Energy, seeking private partners
- Size
- Up to about 100,000 acres offered
- Investment
- Not disclosed
- Status
- DOE named INL one of four federal sites for private AI data centers in July 2025 and took applications through November 2025. We found no developer selection for INL; DOE has announced picks at Savannah River and Paducah. Separately, Aalo Atomics and Crusoe announced in July 2026 a small reactor-powered demonstration data center at INL for 2027.
- Tax break
- Not applicable yet.
- Power
- DOE prefers new nuclear or geothermal power. The Aalo demonstration pairs a 10 MWe reactor with a modular data center.
- Water
- DOE will not lend its federal water rights; developers must acquire Idaho water rights.
- Local rules
- Federal land.
Unconfirmed: Whether DOE has chosen an INL developer since August 2026.
Sources (3)
OperatingLast change Apr 7, 2026
- Developer
- Megalodon Mining and Electric, a T-REX Acquisition Corp. subsidiary
- Size
- About 6,500 sq ft
- Investment
- Not disclosed
- Status
- A small cryptocurrency mining and colocation site, refinanced in April 2026.
- Tax break
- Not reported.
- Power
- Not reported.
- Water
- Not reported.
- Local rules
- None found.
Sources (2)