The Idaho StackSend a tip

Tracker · Public tech money

Idaho’s data center rush, tracked.

Developers want to put some of the largest electricity customers in the state’s history in Kuna, Pocatello, the desert south of Boise and beyond. This page follows every project on the public record: who is building, how much power it wants, what tax break it can claim, and what local governments have done about it. It is rebuilt from public records every week.

Data checked Nov 8, 202611 projects · 10 local actionsNext update: weekly, or when a record changes
11

data center projects on the public record in Idaho: 2 operating, 2 approved, 5 proposed, 1 on hold and 1 denied and in court.

$4.8B

in announced investment across the 4 projects that named a figure. Announcements are not spending.

4,000 MW

of large-load requests in Idaho Power’s pipeline, its CEO told investors October 29, after 76 inquiries over 1 MW so far in 2026. source

Dec 14

left to comment on how Idaho Power splits its costs, including for data centers (case IPC-E-26-07). source

Every project

Where they want to build.

Tap a number on the map to jump to that project, or filter by where each one stands. Each card shows the date of its latest public change and links to the records behind it. Anything we could not confirm in a primary or reputable source is flagged.

Map of Idaho showing 11 data center projects by status, with a close-up of the Treasure Valley Coeur d’AleneLewistonIdaho FallsTwin Falls7891011TREASURE VALLEYBoiseNampaKunaMountain Home123456
  • Operating2
  • Approved2
  • Proposed5
  • On hold1
  • Denied, contested1
1

Kuna · Ada County

Meta Kuna Data Center

OperatingLast change Sep 4, 2026

Developer
Meta Platforms (utility customer of record: Brisbie, LLC)
Size
960,000+ sq ft
Investment
$1.2B Meta’s 2026 figure; $800M when announced in 2022
Status
Serving traffic as of September 2026, according to a Meta executive’s post reported by Baxtel. Announced February 2022 with about 100 permanent jobs.
Tax break
BoiseDev describes Meta as eligible for the 63-3622VV sales tax exemption. 2025 Senate committee minutes record conflicting testimony on whether the Tax Commission granted it. No public record shows the amount. Our note.
Power
Special contract with Idaho Power under the name Brisbie, LLC, approved by the PUC May 11, 2023 (case IPC-E-21-42). Meta says it added 645 MW of new renewable supply in Ada County to match its use. Neither Meta nor Idaho Power has published the site’s load in megawatts.
Water
Meta transferred about 2.5 million gallons a day of farm water rights to the City of Kuna and runs the site on a separate system. Expected summer peak use is just under 2 million gallons a day, BoiseDev reported.
Local rules
Inside the Kuna East urban renewal district, created in 2022.
Sources (5)
2

Kuna · Ada County

Gemstone Technology Park

On holdLast change Jun 15, 2026

Developer
Diode Ventures, a Black & Veatch subsidiary (applicant: Gemstone Technology Park LLC)
Size
620 acres, up to 5 buildings
Investment
$1B “more than $1 billion,” per the developer
Status
Kuna approved the rezone April 1, 2025, on a tie broken by the mayor. Neighbors sued; a district judge denied their petition in May 2026 and they appealed to the Idaho Supreme Court in June. No hearing date was set as of August. Design review is still ahead.
Tax break
Could qualify for 63-3622VV, BoiseDev reported. No record shows a claim.
Power
Idaho Power has completed a feasibility study; the developer says it will pay all interconnection upgrades. No PUC contract found. The Idaho Conservation League estimates 600 to 800 MW; the developer has not published a figure.
Water
Plans to move three irrigation water rights, about 1.63 million gallons a day, to industrial use through a pending Idaho Department of Water Resources transfer, with on-site treatment and reinjection.
Local rules
The developer offered about $40 million to Kuna’s fire district, police and schools.
Sources (4)
3

Boise · Ada County

ValorC3 Emerald

ApprovedLast change Mar 26, 2026

Developer
ValorC3 (formerly Fiberpipe), owned by Tonaquint
Size
10 MW · 38,000 sq ft first phase
Investment
$20M “more than $20 million” for phase one
Status
Boise approved the first phase in 2025, due to open in 2027. A preliminary application in March 2026 would add 31,000 sq ft.
Tax break
Below the $250 million threshold for 63-3622VV.
Power
Not reported.
Water
Not reported.
Local rules
A colocation site inside Boise city limits, approved before the mayor’s November 2026 moratorium proposal.
Sources (1)
4

Nampa · Canyon County

T5 Data Centers Nampa

ApprovedLast change Sep 2, 2025

Developer
T5 Data Centers, for one unnamed tenant
Size
8.25 MW · 80,000+ sq ft existing building
Investment
Not disclosed
Status
Nampa’s planning commission approved a conditional use permit in August 2025 to convert an existing building in Park 84. Whether it is operating is not reported.
Tax break
Not reported.
Power
About 2.25 MW at first, rising to 8.25 MW, BoiseDev reported. Another outlet put the first stage at 2.5 MW.
Water
Air-cooled; the developer compared water use to one or two homes.
Local rules
Conditional use permit from Nampa.
Sources (1)
5

Southeast of Boise (BLM land) · Ada County

Rhea Data, Blacks Creek

ProposedLast change Oct 9, 2026

Developer
Rhea Data, a subsidiary of Nevada-based Arevia Power
Size
600 MW · About 4 million sq ft on roughly 3,200 to 3,750 acres
Investment
Not disclosed
Status
Applied to the Bureau of Land Management’s Four Rivers Field Office to use public land south of Kuna-Mora Road. The BLM expects to open formal environmental review with public comment around the end of 2026.
Tax break
Not reported.
Power
600 MW of computing, per the applicant. An on-site gas plant of about 450 MW appears in the applicant’s early filings; the BLM has not confirmed the energy plan. Idaho Power says Rhea is not in its load forecast and any service would need PUC review.
Water
Not reported.
Local rules
Federal land, so the BLM decides, not a city or county. Boise’s mayor called selling public land for mega data centers “shortsighted.”

Unconfirmed: Acreage varies by outlet (3,226; 3,200; about 3,700; about 3,750). The gas plant size comes from one outlet’s reading of the filings.

Sources (4)
6

Mountain Home · Elmore County

Bennett Ranch Industrial Campus

ProposedLast change Oct 27, 2026

Developer
Weitz & Co.
Size
About 3.4 million sq ft in four buildings
Investment
Not disclosed
Status
A concept was dropped off at City Hall on October 20, 2026. No land-use application has been filed. A week later the city adopted an emergency moratorium on data center applications.
Tax break
Not reported.
Power
The concept includes its own power generation and backup power. Size not stated.
Water
Closed-loop cooling proposed. A 2005 agreement may allow a city water connection, KIVI reported.
Local rules
Data centers are not a permitted or conditional use in any Mountain Home zone, the mayor said. Emergency moratorium adopted October 27, 2026.
Sources (2)
7

South of Shoshone (BLM land) · Lincoln / Jerome County

Copia Digital “Falcon”

ProposedLast change Oct 27, 2026

Developer
Copia Digital
Size
About 3,000 to 3,700 acres
Investment
Not disclosed
Status
A pre-application to the BLM filed in January 2026 for public land near Idaho Power’s Midpoint substation. The developer says formal federal review is likely at least a year away.
Tax break
Not reported.
Power
Not disclosed. The site sits near the Midpoint substation, a major transmission hub.
Water
Not reported.
Local rules
Federal land; the BLM decides.

Unconfirmed: Acreage: about 3,013 acres in one analysis of the application records, about 3,700 in another report.

Sources (1)
8

East of Declo · Cassia County

TerraVolt Campus

ProposedLast change Oct 30, 2026

Developer
TerraVolt Holdings (formerly CalEthos), Tustin, Calif.
Size
240 MW · Options on 1,077 acres
Investment
Not disclosed
Status
Announced options to buy 1,077 acres on October 30, 2026. Data centers are not a permitted use in Cassia County, so the project needs county zoning approval. Commissioners hold a public meeting November 10.
Tax break
Not reported.
Power
240 MW of gas generation on site, separate from the grid, fed by the Williams Northwest Pipeline under a supply deal announced in May 2026.
Water
The company says closed-loop or low-water cooling will be required of each site buyer.
Local rules
Needs Cassia County zoning approval.
Sources (4)
9

Pocatello · Bannock County

Lex Developments AI campus (former Hoku plant)

Denied, contestedLast change Oct 26, 2026

Developer
Lex Developments LLC, Gilbert, Ariz.
Size
100 MW · Seven buildings, about 700,000 sq ft
Investment
$2.6B
Status
Pocatello denied a conditional use permit in May 2026 and upheld the denial twice, most recently 3-2 on September 17. The developer petitioned the Sixth District Court for judicial review in late October, arguing no permit was needed in the industrial zone. It also says it plans to reapply; the council waived the usual one-year wait.
Tax break
Not reported. BoiseDev noted it could qualify for Idaho’s property tax cap for $1 billion-plus investments, a separate break.
Power
An Idaho Power feasibility letter cites more than 100 MW by 2031. The developer has also said the site could host up to 300 MW of gas generation.
Water
No wastewater figure was given to the city.
Local rules
The Shoshone-Bannock Tribes and more than 80 speakers at the first hearing opposed it. Bannock County separately adopted a moratorium for unincorporated areas.
Sources (4)
10

INL desert site, west of Idaho Falls · Butte / Bingham / Bonneville / Jefferson County

Idaho National Laboratory AI data center site

ProposedLast change Jul 30, 2026

Developer
U.S. Department of Energy, seeking private partners
Size
Up to about 100,000 acres offered
Investment
Not disclosed
Status
DOE named INL one of four federal sites for private AI data centers in July 2025 and took applications through November 2025. We found no developer selection for INL; DOE has announced picks at Savannah River and Paducah. Separately, Aalo Atomics and Crusoe announced in July 2026 a small reactor-powered demonstration data center at INL for 2027.
Tax break
Not applicable yet.
Power
DOE prefers new nuclear or geothermal power. The Aalo demonstration pairs a 10 MWe reactor with a modular data center.
Water
DOE will not lend its federal water rights; developers must acquire Idaho water rights.
Local rules
Federal land.

Unconfirmed: Whether DOE has chosen an INL developer since August 2026.

Sources (3)
11

Orofino · Clearwater County

Orofino bitcoin mining center

OperatingLast change Apr 7, 2026

Developer
Megalodon Mining and Electric, a T-REX Acquisition Corp. subsidiary
Size
About 6,500 sq ft
Investment
Not disclosed
Status
A small cryptocurrency mining and colocation site, refinanced in April 2026.
Tax break
Not reported.
Power
Not reported.
Water
Not reported.
Local rules
None found.
Sources (2)

Who pays for the power

Idaho rewrote the rules this year. The bill is still being split.

Two 2026 laws now govern new data centers. One makes any new load of 50 MW or more pay its full cost of service under a contract the Public Utilities Commission must approve. The other bars new data centers from consuming water for cooling unless it comes from a city or water district system. How Idaho Power’s costs are divided between big new customers and everyone else is being argued in an open PUC case right now.

  1. PUC approves Meta’s power contract

    Order 35777 in case IPC-E-21-42 set the terms for Brisbie, LLC: the first 20 MW at standard large-customer rates, everything above at Idaho Power’s marginal cost. source

  2. Idaho Power opens the cost case

    Its petition in IPC-E-26-07 asks the PUC to review how costs are assigned to customer classes and what to weigh for new large loads. It proposes no new tariff. source

  3. Cooling water law signed

    HB 895 (Idaho Code 42-252): data centers that begin construction after July 1 may not use water consumptively for cooling unless it comes from a city or water district system. source

  4. Large-load law signed

    HB 911 (Idaho Code 61-335): from July 1, new loads of 50 MW or more need a PUC-approved contract that passes a no-harm test, pay their full cost and post security against stranded costs. source

  5. Micron’s contract approved

    The PUC approved Micron’s fab power contract with changes and sent remaining cost questions to the open cost case. source

  6. Idaho Power: about 4,000 MW in the pipeline

    Executives told investors the large-load pipeline is “right about 4,000 megawatts,” about a quarter of it promising, and that Meta began operating in September. source

  7. PUC staff and intervenors file

    First public positions from PUC staff, Micron, irrigators, industrial customers, Boise and clean energy groups. source

  8. Public comment deadline

    Last day for written public comments in IPC-E-26-07. source

  9. Technical hearing

    At PUC offices in Boise, continuing January 20 and 21 if needed. source

Local rules

Towns and counties are writing the rules as they go.

Idaho has no statewide siting rules for data centers, so zoning decisions fall to cities and counties. These are the actions we have found so far.

City and county actions on data centers, newest first
WhereActionWhat it doesDateRecord
BoiseMoratoriumCouncil unanimously adopted a 182-day emergency moratorium on data centers of 100,000 sq ft or 20 MW and up, effective immediately, with no application pending. Interim rules of up to 12 months could follow.Nov 10, 2026source
Mountain HomeMoratoriumEmergency moratorium on data center applications and permits, a week after a 3.4 million sq ft concept reached City Hall. Idaho law caps emergency moratoriums at 182 days.Oct 27, 2026source
Blaine CountyMoratorium182-day emergency moratorium, passed 3-0 with no application pending, while staff draft zoning rules for three light-industrial zones, including one north of Hailey.Oct 6, 2026source
PocatelloPermit deniedCouncil upheld, 3-2, its denial of Lex Developments’ $2.6 billion campus at the former Hoku plant, and waived the one-year wait to reapply. The developer has gone to court.Sep 17, 2026source
SandpointBan, reported passedCouncil took up a code change banning data centers over 5,000 sq ft in the city’s industrial park zone, after its planning commission called the cap arbitrary. Local press reported approval on September 18; we could not open that report.Sep 16, 2026source
Latah CountyRules adoptedCommissioners unanimously adopted rules on water, power, noise and setbacks for future data centers. None exists or is proposed in the county.Sep 15, 2026source
Coeur d’AleneResolutionCouncil voted 5-0 for a non-binding resolution opposing new or expanded data centers until the city finishes studying them. Zoning still allows them with a permit.Aug 4, 2026source
PonderayUnder discussionCouncil discussed a staff draft excluding data centers from city code. No vote taken.Aug 3, 2026source
Bannock CountyMoratorium180-day emergency moratorium for unincorporated areas, through January 26, 2027. A regional work group is drafting a model ordinance.Jul 30, 2026source
Kootenai CountyRules adoptedA 2025 moratorium, adopted to protect the Rathdrum Prairie Aquifer, expired in August 2025 and was replaced by an ordinance that keeps data centers off the aquifer. Commissioners said they wanted a total ban; we found no sign one passed.Oct 2, 2025source

What we don’t know yet

Open questions.

  1. Which companies hold Idaho’s data center sales tax exemption, and what it has cost. The Tax Commission publishes neither.
  2. How many megawatts Meta’s Kuna campus draws today, and how much more its planned buildings would add.
  3. Which project is the “unnamed” data center Idaho Power has added to its preliminary 2027 load forecast.
  4. Whether any contract has been filed under the new 50 MW large-load law, which starts a 270-day PUC review.
  5. Whether DOE has picked a developer for the INL site, and whether Boise follows its 182-day moratorium with interim rules of up to 12 months.

Notes on the numbers

Megawatt and dollar figures are what developers or public bodies announced. They measure different things (computing capacity, utility load, on-site generation) and should not be added together. Kuna’s figures show the gap: Meta’s 2026 investment figure is $1.2 billion, up from $800 million at announcement, and estimates of its water use differ by outlet.

We leave out small server rooms and colocation sites listed only by commercial directories, and Avista’s 500 MW data center customer, which Avista places in Washington.

Know of a project we’ve missed, or a record that changed? Send a tip or write hello@idahostack.com.

Method

How this is built.

We list a project once a developer, utility, regulator or local government has put it on the public record, and keep it after a denial so the history stays visible. Sizes and dollar figures are what the developer or a public body announced, not what has been spent. Every row links to its records and shows the date of its latest change. The tracker was compiled from public documents and news reports and reviewed by the editor before publication. No interviews, site visits or company contacts were part of this version.